Pudu Prison wall makes way for wider road

June 17, 2010
KUALA LUMPUR, June 17 — The 300m stretch of the Pudu Prison wall along Jalan Pudu will be demolished on June 20-23 to make way for road widening and the construction of an underpass.

Kuala Lumpur Mayor Datuk Ahmad Fuad Ismail said the construction of the underpass gave priority to road users although it involved a national treasure.

“Every day we face problems because of this wall, getting to the office late, so this is just a matter of which one is a priority to DBKL (Kuala Lumpur City Hall) and the government,” he told reporters after visiting the site and Taman Shamelin Perkasa.

The underpass will be an alternative route linking Jalan Pudu to Cheras and will reduce congestion at Jalan Hang Tuah.

Construction will be carried out in stages and the project is expected to be completed in December 2012.

Meanwhile, the construction of the RM59.5 million flyover directly connecting Taman Maluri with Taman Shamelin, which started in March last year, is expected to be completed in March 2012. — Bernama